Resurfacing work starts tomorrow on the M23 junction 9 roundabout, and the Gatwick Spur Road and Airport Way slip roads.
The work will be completed in three phases overnight from Monday to Friday from 9pm to 5am. During the first phase, from 7th to 22nd January, the northbound off slip road will remain open whilst the other slip roads will be closed overnight.
Traffic wishing to exit the M23 at junction 9 southbound will need to continue down the motorway to junction 10 to turn around and rejoin the M23 northbound. Traffic wishing to use the M23 eastbound Spur Road to join the motorway will be diverted via Airport Way and the A23 London Road to turn around at the Longbridge Roundabout.
The final phase of works should be completed on 13th February.